USD 489 makes progress on Hays High HVAC; bond moving forward

HVAC Expert July 22, 2022

By CRISTINA JANNEY
Hays Post

The Hays USD 489 school district is on schedule to complete a couple of major capital projects this summer. The district is also moving forward with its $143.5 million bond issue.

The first phase of the $6 million Hays High School HVAC project is nearing completion. Superintendent Ron Wilson said water should be back in the system and air conditioning functioning in the building by the end of the week.

The second phase of the project will be completed next summer.

Air Conditioning Riser
Air Conditioning RiserRead more

Work is also on track for the replacement of windows at O’Loughlin Elementary School. The $652,730 project is supposed to be completed by the beginning of the school year. It also included replacing windows at Wilson Elementary School and Rockwell Administration Center.

The board on Monday approved a bid for $165,258 from Commercial Builders for concrete paving at the district’s transportation facility. That work will begin before the end of the year but be finished after the start of school.

Arrangements have been made to park the buses outside of the fence while the concrete work is being done.

Bond progress

Wilson reported to the board that 10 teachers and administrators recently toured high schools that had work completed by the district’s architectural firm, DLR.

The trip was meant to help in the planning process for the new high school. The group visited high schools in Tonganoxie, Ottawa, Salina and Lee’s Summit, Mo.

“We’ve seen pictures and gotten excited, but when you’re walking in those spaces and knowing we are going to have something as good or better. … It’s going to be unbelievable,” Wilson said.

A Kansas Department of Transportation grant will be used to do a traffic study of 13th Street and Canterbury near the new high school. Some residents raised concerns during the bond election about congestion in the area when the new school is built.

The board also approved the letting of bonds for the bond projects at its meeting Monday.

Wilson said the district has been advised by its bond counsel that conditions may be favorable soon to let the bonds. The school district has already started the process of obtaining a bond rating, which Wilson said he thought would be favorable.

Wilson said the City of Hays also will soon take up a measure that will annex the 41 acres of land for the new high school, which is currently in the county. The land for the high school also will need to be rezoned.

iPads

The district approved the purchase of 800 student iPads and cases for Hays Middle School.

The district applied for $320,000 in emergency connectivity funds to help pay for the devices. The total cost of the devices is $354,360.

The district has yet to hear back about the grant, but could still be reimbursed if the grant is awarded.

Board elections

“/>New Hays USD 489 school board vice president Ken Brooks, left, and president Craig Pallister. Photo by Cristina Janney/Hays Post

The board conducted its annual reorganization meeting Monday. Craig Pallister was elected president, and Ken Brooks was elected vice-president.

Pallister, who has served as vice-president of the board for the past year, takes over the role from Tammy Wellbrock.

Westside school update

USD 489 makes progress on Hays High HVAC; bond moving forward

Prev Article
Next Article

About The Author

HVAC Expert

Recent Posts

  • Is Central Air Gas Or Electric
  • Hvac Cost Per Square Foot
  • How Does Ac Freeze Up
  • How Does Central Air Work In Apartments
  • How To Clean Hvac Unit

AIR CONDITIONING SERVICING

AIR CONDITIONING SERVICING DAILY
Copyright © 2025 AIR CONDITIONING SERVICING
Theme by Air Conditioning Servicing

Ad Blocker Detected

Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by disabling your ad blocker.

Refresh